Castleton Project Updates – Week of 7/22/19

Castleton Project Updates – Week of 7/22/19

The Affordable Paving team is doing our very best to complete project phases in a timely fashion but there is an extensive amount of repairs that are required to finish this job correctly. We apologize for the inconveniences and appreciate your cooperation and understanding throughout this process.

Here is the planned schedule for next week. 

Monday 7/22

  • Continue milling and prepping the main entrance off of 441 connecting to the main intersection of the townhomes (Section 5).

Tuesday 7/23

  • Paving Section 5
  • Milling the road where the dumpsters are located
  • Milling Shadetree Blvd. from Sable Dr. to Daplin Ave.

Wednesday 7/24

  • Paving the road where the dumpsters are located.
  • Paving Shadetree Blvd. from Sable Dr. to Daplin Ave.

The intersection and main roads will all be opened back up by Thursday.  (Weather Permitting)

Please no parking on either side of the dumpsters as we need to stage our equipment in this area.