Castleton Community – Marietta, PA

Castleton Community – Marietta, PA

Pictured below is a site plan sketch of the alley way Affordable Paving will be working on in the Castleton neighborhood in Marietta, PA.  We are currently prepping to pave sections 1-4.  Section 5 will be done at a later time as new homes are still being built in this area. Section 6 is tentatively scheduled to begin the week of July 8 and a phasing schedule will be provided for that area before we start.

Weather permitting, we will begin the rough/scratch course over the alley starting in Section 1 & 2 on Tuesday 6/25 & Section 3 & 4 Wednesday 6/26.

We will put the final overlay over the alley ways in Section 1 & 2 on Thursday 6/27 &  Section 3 & 4 Friday 6/28.

We will be blocking the access to homeowner driveway/garages from approx. 7am-6pm.  Homeowners will be allowed to drive on the blacktop after 7pm each evening.