We will be prepping the lower part of the development Monday Nov 5th. Street sweeping will begin on Monday Evening starting at 3pm.  No Street Parking Mon – Fri between 5am – 7pm.  We will be petro matting, tack coating and paving Tuesday – Friday Nov 6-9.

Thank you for your patience and cooperation!

We are paving this week starting at the top of the Development with Tait, Cale and Fourth Street and Logan Dr from Steltz Rd to Third Street.

No Street Parking is allow Monday through Wednesday from 5am to 7pm oi all of these areas. We will be sweeping streets, tack coating, petro matting and paving.

Thank you for your patience and cooperation!

The Affordable Paving team will continue pipe flushing on Wednesday, October 24, 2018 on parts of 4t, Kale, Tate, and Logan streets.

Paving is scheduled to begin on Monday, October 29th. No parking in these areas with limited access to driveway while paving.

Cale Drive, Tait Drive, 4th Street and everything on Logan Drive north of fourth Street have all concrete repairs completed except for a few small areas and they will be completed Wednesday, 10/10. All inlets that need addressed throughout the entire development have been replaced or repaired with concrete and they have been cleaned of all debris.

50% of the curb stops in the development there have been repaired or in the process of being repaired. Some of the residents have asked what a curb stop is and it’s basically the underwater valve that the borough uses to shut off the water to your house in case of emergency.

There was over 80 of these that needed repaired in some way shape or form. Many of the storm drain pipes need repaired in the development and over 70% of these are repaired. We are currently looking for any other areas that need base asphalt repairs to complete that in the next week or two the areas where we replaced or repaired storm drain pipes in the roadway and these we left expose until we were able to have the repairs inspected.

Most of this has been completed with only a few remaining areas to go. As the project moves forward we will try to keep everyone updated as much as possible. Any questions or concerns that you have feel free to talk to Tom with Affordable Paving who you may see driving around the job site in a white pickup truck. If you can’t find him just ask where the Affordable Paving workers you see running around the development.

In the meantime, we will continue work on storm drain pipe repairs and base repair paving on all road in development.

Curb Stop repairs will begin on Thursday, October 11, on Third Street, Broad Street, Chelsea Dr and Logan Drive from Third Street to Front Street.  All houses on the list will get a door hanger notifying them of the repair.

In preparation of the future paving of the development we will begin removing asphalt driveway wedges on Monday, October 15, 2018.

Continuing Storm Drain pipe repairs

Continuing Base Repair paving on all road in development

 

Curb Stop repairs will begin on Thursday, October 4, on Fourth Street, Tait Drive, Cale Drive & Logan Drive from Fourth Street to Steltz Rd.  All houses on the list will get a door hanger notifying them of the repair.

Click here for a list of all the curb stops that will need to be repaired. The lower section of the development will be started on Oct 11.

On Thursday, Sept 20 we will begin digging up and repairing storm drain pipes in or between the following houses.

2 Logan Dr – in front corner of yard.

106 and 108 Broad Street – In between houses, front yard near curb.

45 & 47 Third Street – In-between houses – towards the back of the house near their back yards

All locations of drain pipe repairs are marked in pink paint on the ground where we will be digging.

Affordable Paving & Excavating LLC has been contracted to remove and replace concrete sidewalk on or around your property. Please follow all posted “No Parking” signs so we have room to get our equipment in and around the marked areas where concrete is being removed and replaced.

The expected project timeline starting Monday, September 17th is expected to be completed by October 26, 2018.